Evaluations - Evaluation of Infrastructure Canada's Economic Action Plan Initiatives - Chart 17 - text description
Chart 17 – Per cent of Communities Component Top-Up projects and value of projects completed by March 31st by project category – Text Description
Bar graph showing the percentage of Communities Component Top-Up projects and value of projects completed on March 31, 2011 by project category. Number of projects equals 537.
| Project Category | % of Funding | % of Projects |
|---|---|---|
| Water/Wastewater | 29% | 45% |
| Transit | 8% | 40% |
| Other | 45% | 59% |
| Local Roads | 39% | 68% |
| Community | 13% | 36% |
Return to Evaluation of Infrastructure Canada's Economic Action Plan Initiatives