Chart 11 – Per cent of Infrastructure Stimulus Fund projects and value of projects substantially completed by March 31st, 2011 by materiality (total eligible costs) – Text Description
Bar graph showing the percentage of Infrastructure Stimulus Fund projects and value of projects substantially completed by March 31st, 2011 by materiality (total eligible costs).
| Value of projects substantially completed by March 31st, 2011 |
% of Project | % of Funding |
|---|---|---|
| < $75K | 88% | 88% |
| $75K-$150K | 85% | 87% |
| $150K-300K | 78% | 77% |
| $300K-$600K | 75% | 75% |
| $600K-$1.5M | 70% | 70% |
| $1.5M-$3M | 63% | 65% |
| $3M-$5M | 51% | 53% |
| $5M-$15M | 34% | 33% |
| $15M-$30M | 15% | 15% |
| $30M + | 11% | 12% |